Rheinfelden river power plant (D)

April 2008 - (in progress)

 

Construction of power plant with 4x 25 Megawatt turbines in the rhine river including excavation of the river bed and blasting of approx. 1.2 Mio m³ of hardrock.

Claim consulting forcontractor; Judgement on technical and geotechnical claim potentials.

In cooperation with Warning Bauconsult, Munich.

Customer: Sprengarbeiten Flusskraftwerk Rheinfelden JV.